Name: Günes Duru 
Team: IST 
Date: 7/24/2006 
Entry: I think we have one week more days for this year. After the red painted platform which was appear under the 1993 (exist platform) we all wonder the meaning/function of red painting? Mihriban works in the S284 and she wants to clean horn corn, Turhan wo... click here for more... 
 
Name: MO 
Team:  
Date: 7/14/2008 
Entry: Removal of upper floor of Building 63. Excavating in Sp. 283, the burnt room. Cleaning and following the red painted plaster on the northern face of platform 1993. The plan of the features in the building (63) and their stratigraphical positio... click here for more... 
 
Name: MO 
Team:  
Date: 7/17/2008 
Entry: Removal of the north and west walls of Building/Space 253. Removal of the hearth/fire spot under Platform 1993. Following and cleaning the red painted plaster shows the plan of the inner features in Space 285. Following the plaster we found out th... click here for more... 
 