The Excavation Diary

The excavation diaries are a daily log kept by the excavators on site during each season. They record the day to day activity of the team and their observations on their work.
 
Displaying Diary Entries for Feature = 3375

Page 1 of 1 (Total Records: 3)
Name: JMR 
Team:  
Date: 8/20/2012 
Entry: CMF and EUR brushed their Building 105 for its first 3D-Scan. After this, CMF started on removing wall F.3349, which turned out to be quite disturbed, and uncovered nicely the tops of walls F.3352 and F.3350, starting from the northern part moving south. ... click here for more... 
 
Name: JMR 
Team:  
Date: 8/4/2013 
Entry: The team arrived on Friday and cleaned the trench yesterday (Saturday) and today. After cleaning, photos were taken and then excavation started. GWN, ASO and EIH are working in B.98. The aim for this season is to find out what is under floor 16977. For... click here for more... 
 
Name: JMR 
Team:  
Date: 8/20/2013 
Entry: Today was a day of new discoveries. In Space 448, TET and PAB scraped the bottom some more after finishing the big fill layer 31169 yesterday. After that, we saw two spots that very certainly were buttresses, even though they are still fuzzy at this le... click here for more... 
 