Displaying Diary Entries for Feature = 3386 |
Page 1 of 1 (Total Records: 3)
|
Name: | JMR |
Team: | |
Date: | 8/21/2013 |
Entry: | What a day. So much progress.
Towards the middle of the day I got quite stressed, though. B.107. Who would have thought that this would turn out so complicated. Also, I hate those meep meep rodents.
CMP cut a NS section into a part of the eastern wa... click here for more... |
|
Name: | JMR |
Team: | |
Date: | 8/24/2013 |
Entry: | GWN and CLC continued investigating feature and “burnt layer” in the phase under B.98 which now has the working title Building 125! CLC found a corner, so there really is a wall behind the buttress F.3387, of which we do not see the eastern limit. GWN fol... click here for more... |
|
Name: | JMR |
Team: | |
Date: | 8/26/2013 |
Entry: | This is a dairy for 25th August – the last excavation day in Trench 5 for this season – and forever.
DSE in Space 310 removed the marl lumps he uncovered in removing layer 31232 and during removal confirmed that the marl did not form constructed featur... click here for more... |
|
|