Displaying Diary Entries for Unit: 17294 |
Page 1 of 1 (Total Records: 3)
|
Name: | JMR |
Team: | |
Date: | 8/12/2012 |
Entry: | KTX worked further on clarifying the brick work in the area wall F.5058 meets buttress F.3301. This area, as already expected, is quite complicated. The wall makes a slight bend here, and also was connected to the buttress, so we expected brick laying to ... click here for more... |
|
Name: | JMR |
Team: | |
Date: | 8/15/2012 |
Entry: | Last day with our Southampton power team.
DLG, with Harish and Sam, brushed Building 107 really nicely for a 3D photo session done by PTW. After that, they started taking out wall F.3344 from the top. The reason for starting with this wall is that the ... click here for more... |
|
Name: | JMR |
Team: | |
Date: | 8/18/2012 |
Entry: | This is a summary for work done today and also Thursday 16th August.
In Building 105, EUR and CMF worked on removing the mud brick concentrations 18364 in the northeast and northwest corner of the building. In EUR’s northeast corner, the brick material... click here for more... |
|
|