Space Number:  257

Area: South  

 

Within Building Number: 53 

 

Phasing:
Mellaart Level: Unassigned at present 

Hodder Level: South.Q 

Additional Phase Info: Main spine. This space is part of the stratigraphic spine that forms the dating project sequence. The spine has been derived by direct stratigraphic relations as far as possible but does include some abutting relationships. Space257 of B.53 is below Space 260 and associated with middens Sp.261. B.53 is constrcucted over, therefore later than Sp.132. Prior to the introduction of the Hodder phases Sp.257 had been allocated to Mellaart Level VI and a review of the phasing (S.Farid Archive Report 2008) had placed the phasing as more akin to Level V. but Mellaart levels of buildings/spaces NOT excavated in the 1960s have been removed to allow an independent assessment on phasing. NB/Work in progress. Correct as of date entered or modified.Pre 2009 

 

Description:
Space defined by walls F1523, F1524 and F1527. Excavation of space not completed during 2005 season (SMcC) 

 

Number of Related Diary Entries: 3

 

Conservation Recorded: No

Related Photos: 425 (Opens as a group in a new window) 
Feature Numbers Related to this Space: (Click to view the record)

1500 (burial)
1523 (wall)
1524 (wall)
1525 (platform)
1526 (platform)
 
1527 (wall)
1529 (pillar)
1532 (burial)
1534 (wall)
 
1535 (access hole)
1537 (pit/scoop)
1538 (pit/scoop)
1539 (pit/scoop)
 
 
No. Of Units in this Space: 89  (Click to view unit list)

<< BackDownload this Spaces Data

main sponsors

Yapi Kredi

Ko�tas

Boeing

secondary sponsors

Konya Seker

Shell