Name: | PAB |
Team: | |
Date: | 8/25/2013 |
Entry: | Today we continued preparation and cutting down space 525. We were finally able to completely uncover the plaster line which showed us the new building 126 dimensions. The building includes a buttress and had several floors which been cut in previous exca... click here for more... |
|
Name: | JMR |
Team: | |
Date: | 8/26/2013 |
Entry: | This is a dairy for 25th August – the last excavation day in Trench 5 for this season – and forever.
DSE in Space 310 removed the marl lumps he uncovered in removing layer 31232 and during removal confirmed that the marl did not form constructed featur... click here for more... |
|
Name: | JMR |
Team: | |
Date: | 8/29/2013 |
Entry: | For the last four days, we have been working on trench closing tasks. Cleaning, taking millions of photos, taking a few last samples, dismantling the tent, taking more pictures, also from a cherry picker, finishing documentation and finds sorting. Today, ... click here for more... |
|
|