Name: JMR 
Team:  
Date: 8/21/2013 
Entry: What a day. So much progress. Towards the middle of the day I got quite stressed, though. B.107. Who would have thought that this would turn out so complicated. Also, I hate those meep meep rodents. CMP cut a NS section into a part of the eastern wa... click here for more... 
 
Name: GWN 
Team:  
Date: 8/24/2013 
Entry: This is one of the last days for excavation so we are finishing the work in the small sondage bellow the building 98. After closing the 31214 and opening 31227 and 31218, as well as the feature 3387, we determined the earliest building so far in the Tre... click here for more... 
 
Name: JMR 
Team:  
Date: 8/24/2013 
Entry: GWN and CLC continued investigating feature and “burnt layer” in the phase under B.98 which now has the working title Building 125! CLC found a corner, so there really is a wall behind the buttress F.3387, of which we do not see the eastern limit. GWN fol... click here for more... 
 
Name: GWN 
Team:  
Date: 8/25/2013 
Entry: Today is the last excavation day so we had to finish the digging and clearing of our units. Surely it was not possible to close them, neither to explore the buildings in total, especially not the building 125. From Tuesday on, the site will be backfilled ... click here for more... 
 
Name: CLC 
Team:  
Date: 8/26/2013 
Entry: 24-08-2013 In seeking again to further clarify the extent of the buttress feature in the new building 125 (F. 3387), I began excavating the top brownish fill out of the area surrounding the buttress as U 31233, while the lowest 4cm just above the red f... click here for more... 
 
Name: JMR 
Team:  
Date: 8/26/2013 
Entry: This is a dairy for 25th August – the last excavation day in Trench 5 for this season – and forever. DSE in Space 310 removed the marl lumps he uncovered in removing layer 31232 and during removal confirmed that the marl did not form constructed featur... click here for more... 
 