Entry: DLG and PTW finished U.15349, which differs from the other topsoil layers on roughly the same level (15350, 15351) because it contains building materials such as dark grey brick, plaster, lime, burnt red brick and lumps of pale yellow clay. Most of these ... click here for more... 
 
Name: JMR 
Team:  
Date: 7/23/2011 
Entry: Thursday 21st July we continued excavating in the trench extension. DLG continued U.15358 west of Sp.343 and 342. DKK, CMB and EMM continued the massive U.15357 over the southern part of Sp.342, where JFB also excavated, documented and removed the skull o... click here for more... 
 
Name: JMR 
Team:  
Date: 7/24/2011 
Entry: Excavation in the units with much soil went slowly today as the two sifting workman were missing. DLG continued U.15358, CMB and DKK continued U.15357. HLS continued going down and finding the cut in pit F.3331. It is now rather clear that there must be a... click here for more... 
 