Entry: | 28/7/98
Removed floor [2865] up to section line. Planned and excavated ashy deposit [2891] up to section line. Excavated part of layer beneath [2891] - but realised that stratigraphically under some other apparent floor layer(s), that could see in sectio... click here for more... |
|
Name: | Richard Turnbull |
Team: | Çatal |
Date: | 8/1/1998 |
Entry: | 1/8/98
Finished planning and excavated ashy deposit [2891]. Planned and excavated possible structural part of F.87 or earlier phase [3116] also general layer - skim of brown silt [3118] . Planned / excavated another possible structural element of F.87 or... click here for more... |
|
|