Displaying Diary Entries for Unit: 13703 |
Page 1 of 1 (Total Records: 9)
|
Name: | Christoph Skowranek Doru |
Team: | West-Buffalo/Camb |
Date: | 7/24/2006 |
Entry: | Today we started working at 6 am, it was great! Cool outside and not so much people in the morning.
But I heared at lunch that we woke up some people by slamming doors and so on, wondering cause I heard not so many slammed doors and we were quiet in the ... click here for more... |
|
Name: | Naoise Mac Sweeney |
Team: | West-Buffalo/Camb |
Date: | 7/24/2006 |
Entry: | After an early start we finished cleaning back area 5/unit 13702 for photography and planning. Following this we cleared the eastern half of area 5 - unit 13703 - which falls downslope to the edge of the mound.
Tom and I also practised our Total Sta... click here for more... |
|
Name: | ER |
Team: | West-Buffalo/Camb |
Date: | 7/24/2006 |
Entry: | Today, we started at 6 o'clock in order to use the cooler morning hours which did not prove to be a huge success; rather, we lost almost two hours in long discussions about if and what and when to take photographs, to get the Total Station going (Tom and ... click here for more... |
|
Name: | ER |
Team: | West-Buffalo/Camb |
Date: | 7/25/2006 |
Entry: | Start at 6 o'cock, with the full team, later the workmen hd to help set up the tent. Warm, windy, agreeable conditions.
In A, Christop and Necat dug down into the apparently still quite mixed and eroded slope continuing unit 13703. Here and there patc... click here for more... |
|
Name: | ER |
Team: | West-Buffalo/Camb |
Date: | 7/26/2006 |
Entry: | Full team, except the workmen who continued to help set up the tent over trench 5 and started at trench 6. They were also engaged in fencing the mound. Weather warm and sunny, gentle wind. The tent actually helps a lot in seeing the structures. Jonathan a... click here for more... |
|
Name: | Esra Nigar Irmak |
Team: | West-Thrace |
Date: | 7/27/2006 |
Entry: | Entered By: eni |
|
Name: | Gülay Yilankaya |
Team: | West-Thrace |
Date: | 7/28/2006 |
Entry: | 26/07/2006"da 6 nolu acmada calismaya devam ettik. Acmanin guney bati kisminda tesviye yapmaya basladik. Mezar olabalecek tas kumeler'n'n etrafini temizledik. Cok sayida canak comlek parcalari, kemik ve obsidien bulduk. Acmadan cok sayida gec donem mezarl... click here for more... |
|
Name: | Gülgün Gürcan |
Team: | West-Thrace |
Date: | 7/29/2006 |
Entry: | on 27/07 in the morning I was given an information how to use and set up total station by Nick. Then I exlpained to Esra in Turkish the same prosses. Afterwards I worked in trench 6 unit number 13801 cleaned the surface area and serached for sherds and o... click here for more... |
|
Name: | Esra Nigar Irmak |
Team: | West-Thrace |
Date: | 7/29/2006 |
Entry: | bugun trench 6 da calismayla gune basladim.guney kisimda toprak inilmesine devam edildi.daha sonra yuzey temizlemes yapildi ve supuruldu.yuzey temizligi yaoilirken uzerinde hayvan kabartmasi olan bir seramik parcasi ele gecti. Bugun gulgunun gunu... click here for more... |
|
|