Entry: We finished removing the top soil (15345) today, brushed and fotographed the trench extension afterwards. Already, archaeological contexts start appearing. Over Sp.342, directly on the trench section, a cluster of human bones (F.3340) was found, excavated... click here for more... 
 
Name: JMR 
Team:  
Date: 7/19/2011 
Entry: We are moving pleasingly fast in the trench extension of Trench 5. The only limiting factor to the speed of the excavation is the soil sieving, so we are currently working on three sieves. JHB and RHB finished U.15351 over Space 454. They went down to th... click here for more... 
 
Name: RHB 
Team:  
Date: 7/19/2011 
Entry: My first diary entry of the season! Starting to make some real progress as we finished excavating the arbitrary layer, U.15351 with JHB and we can now see the top of a wall complete with mortar and also a darker area of soil which may be a pit. I spent mo... click here for more... 
 