The Excavation Diary

The excavation diaries are a daily log kept by the excavators on site during each season. They record the day to day activity of the team and their observations on their work.
 
Displaying Diary Entries for Unit: 31124

Page 1 of 1 (Total Records: 6)
Name: NMR 
Team:  
Date: 8/6/2013 
Entry: I started the day with cleaning the exposed part of west-profile of wall F5074. Then I decided to start from the top and to first remove the inter-wall fill between F5074 and F2429, so as to be able to collect it as a separate unit. And at the same time t... click here for more... 
 
Name: NMR 
Team:  
Date: 8/7/2013 
Entry: Today I continued working with DSE on the unit 17247 (F2429). The brushing doesn’t show much more than yesterday, so we will go on with the pic and lower the wall down to the level where it seems to have conserved its original width (the upper part is dis... click here for more... 
 
Name: JMR 
Team:  
Date: 8/8/2013 
Entry: This is a diary for the 6th and 7th August. Currently we are on a 3-day Bayram excavation break, there is no work being done in the trench on the 8th, 9th (Friday anyway) and 10th August. TET and DAB started removing room fill layer 31127 in Space 310.... click here for more... 
 
Name: DSE 
Team:  
Date: 8/11/2013 
Entry: After the three day break of the Bayram work continued at the point we stopped. However NMR started to work on another unite while I stayed with unit 17247. I continued leveling down the unit to an arbitrary drawn layer. A spot with burned grains have bee... click here for more... 
 
Name: DSE 
Team:  
Date: 8/13/2013 
Entry: Today unite 17247 and unite 31124 were finally closed. The last rests of the eastern wall were leveled and the surface cleaned. The unites were photographed together with feature 5074. Afterwards the finds were sorted. The biggest groups of finds are of b... click here for more... 
 
Name: DSE 
Team:  
Date: 8/16/2013 
Entry: This is the Report for the 15.08.2013: Today I finished the units 31124 and 31179. After removing the interfill (31124) and going further down at F. 3306 (unit 31179), the west profile of feature 5074 showed a swift of the plaster line at unit 18351. I... click here for more... 
 