The Excavation Diary

The excavation diaries are a daily log kept by the excavators on site during each season. They record the day to day activity of the team and their observations on their work.
 
Displaying Diary Entries for Unit: 31126

Page 1 of 1 (Total Records: 6)
Name: JMR 
Team:  
Date: 8/8/2013 
Entry: This is a diary for the 6th and 7th August. Currently we are on a 3-day Bayram excavation break, there is no work being done in the trench on the 8th, 9th (Friday anyway) and 10th August. TET and DAB started removing room fill layer 31127 in Space 310.... click here for more... 
 
Name: JMR 
Team:  
Date: 8/14/2013 
Entry: NMR is continuing to do a fabulous job with the plaster layers in Sp.454. She finished the part where the layer run up to the wall. I really want to hit this thing underneath to find out whether it is fill or brick material, but we will have to be patient... click here for more... 
 
Name: GWN 
Team:  
Date: 8/14/2013 
Entry: The diary for 07.08.2013 The work on the installation was during the whole excavation day. Although small in dimensions it has a lot of elements not well exposed, so a cleaning of the whole rim and interior was necessary. After the removal of the fil... click here for more... 
 
Name: GWN 
Team:  
Date: 8/14/2013 
Entry: After my arrival from Macedonia I continued the work on the installation (unit 31126). The remaining fill and dirt on particular areas of the installation were cleared, so its outlines were much more apparent than before. It could be easily seen that enti... click here for more... 
 
Name: TSK 
Team:  
Date: 8/25/2013 
Entry: A lot of points from the total station were the start of my day. There were many units to be closed and therefore many bottom levels to be taken. After this was finished, I started a small section on the Feature 3385 which GWN excavated before. As it was ... click here for more... 
 
Name: JMR 
Team:  
Date: 8/26/2013 
Entry: This is a dairy for 25th August – the last excavation day in Trench 5 for this season – and forever. DSE in Space 310 removed the marl lumps he uncovered in removing layer 31232 and during removal confirmed that the marl did not form constructed featur... click here for more... 
 

Page: [1 ]

 
<< BackDownload these Entries
 

main sponsors

Yapi Kredi

Ko�tas

Boeing

secondary sponsors

Konya Seker

Shell