Entry: JFB, BOD and XHB finished excavating burial F.3317 which will be drawn tomorrow. Burial F.3316, its extensions defined by BOD through scraping (15146) turned out to be partially under F.3317 and can therefore only be started after 3317 is removed. The ... click here for more... 
 
Name: JMR 
Team:  
Date: 8/6/2010 
Entry: Diary entry for 5/8/2010 JFB finished documenting and taking out burial F.3317 and moved over to the next one, F.3318. Sor far, the upper body of 3318 is exposed and turned out to be very well preserved. It might be possible that the lower body is not ... click here for more... 
 
Name: JMR 
Team:  
Date: 8/7/2010 
Entry: EMM finished documenting the present state of excavation in Space 341 and moved over to the area east of buttress F.5057, where several large potsherds became visible during excavation last year. Some of them belong to what seems to be a pit (15160, 15162... click here for more... 
 
Name: LKH 
Team:  
Date: 8/7/2010 
Entry: Unit 15144 is a room fill in Space 340 that I have excavated for the past three or four days. I believe it represents a filling event in which the plastered and red-painted walls of a room or structure were thrown haphazardly away. The walls of the unit... click here for more... 
 
Name: lkh 
Team:  
Date: 8/7/2010 
Entry: Unit 15144 is a room fill in Space 340 that I have excavated for the past three or four days. I believe it represents a filling event in which the plastered and red-painted walls of a room or structure were thrown haphazardly away. The walls of the unit... click here for more... 
 

Page: [1 ]

 
<< BackDownload these Entries
 

main sponsors

Yapi Kredi

Ko�tas

Boeing

secondary sponsors

Konya Seker

Shell