Displaying Diary Entries for Feature = 483 |
Page 1 of 1 (Total Records: 4)
|
Name: | Richard Turnbull |
Team: | Çatal |
Date: | 5/30/1999 |
Entry: | Continuing to work in what is now Space 173. The original plan was to take down wall F.484 once I had taken the fill out of the crawlhole ( now F.487 ) but I decided against that this morning - partly because I wanted to wait until I could get photos of t... click here for more... |
|
Name: | Nurcan Yalman |
Team: | Çatal |
Date: | 5/26/1999 |
Entry: | Diary up to 26.5.99
19/05/99
Today I cleaned the top of the truncated wall (79) by scraping to make its southern edge clear. It seems that the wall had leaned to the south. After lunch I have drawn the edge of the fill where in space 116 beside the wa... click here for more... |
|
Name: | Nurcan Yalman |
Team: | Çatal |
Date: | 6/7/1999 |
Entry: | Entries up to 07.06.99
30.05.99
Today removing of 483 wall almost finished. Also the fill between 483-79 walls appeared but there were some changings in the western half of the fill which looks more bricky and the eastern half was implying charcoal... click here for more... |
|
Name: | Richard Turnbull |
Team: | Çatal |
Date: | 6/13/1999 |
Entry: | Note: in space 173/163 the crawl-hole I originally numbered as F.487 has been renumbered as F.500 as I took out an existing number.
Took down wall at the north end of space 173. ( F.483 ) to about 0.20m above floor
level, after first removing wall pl... click here for more... |
|
|